How to Calculate Individual Target & Line Target?
Already we learn how to Calculate SMV from earlier post. Today we will know the using of SMV.
SMV Formula= Basic time + Allowance
If an operation SMV is .75 means to complete that task by this time.
We can get total garments SMV by sum of each operational SMV. If a garments total SMV is 12 min means from first machine to output , we will get a complete garments by 12 min.
To calculate individual operator target hourly & daily we must need that operational SMV. After having operation SMV, we can calculate his / her hourly target.
Target = (60/SMV )*Efficiency %
This way we will get each operation target hourly by considering each operation separately.
If you want to find total target in a day,
Target = (M.P*W.H*60/SMV)*Efficiency %
Here, W.H = Total working hour he/she will perform
& M.P = No of Manpower.
For example: SMV of an operation is 0.75, No of operator 1, Total working hour 10 & targeted efficiency 85%, then calculate target =?
Target = (1*10*60/.75)*85%
=800*85%
=680 pcs
By this equation we can calculate total day target of a particular line/module. For example, SMV of a garments is 12, No of operator 22, Total working hour 10 & required efficiency 85%, then calculate target =?
So Target = (M.P*W.H*60/SMV)*Efficiency %
=(22*10*60/12)*85%
=(13200/12)*85%
=1100*85%
=935 pcs.
If we want to calculate target at 100% efficiency then put 100% instead of 85%.
Read also: How to calculate Efficiency of a line?