Most Important Formula For Industrial Engineer in Manufacturing Unit
Here are Some Useful Equation of Industrial Engineer.
1. Line Efficiency = (
Total Output*SMV*100)/(Manpower *Working Hour*60)
2. Target = (
Manpower*Working Hour*60*Efficiency%)/SMV
3. Required Manpower
=(Target*SMV)/ (Working Hour*60*Efficiency %)
4. SMV = (Manpower*Working
Hour*60*Efficiency%)/Output
5. Required Working Hour =
(Target*SMV)/ (Manpower*60*Efficiency %)
6. Individual Hourly Target
= (60 *Efficiency)÷ Operation SMV
7. Individual Day Total
Target = (Total Working Hour * 60*Efficiency) /SMV
8. Individual Operator Efficiency =(Total Output * Operation SMV*100)÷(Total Working Hour*60)
9. Individual Performance = Output ÷ Target (For Hourly Monitoring)
10. Machine Productivity = Total Output ÷ No. of machine use
11. Line WIP = Total Cumulative Input - Total Cumulative Output
12. Labor Productivity = Total Output ÷ No. of Operator
13. Pitch Time = Total Garments SMV ÷ Total No Of Operations
Or, = Total Garments SMV ÷ Total No Of Operator
Equation makes our life very easy...
Here all equation in a image format for your assistance. You can download & collect it for the future.
Most Useful Formula for Industrial Engineer |
Product may different But IE equation always same for all kind of RMG unit.
Read Also: How to Increase Line Efficiency while Achieving Even Less?